I am a plumbing contractor. I have a contract with the homeowner for the amount to be paid during each phase of plumbing, there are 3. The first phase is done, and the 2nd phase is done, but the homeowner refuses to pay. How do I get my money from this person?
1 ANSWER
You would stop work due to the home owner's material breach of your contract, and sue the home owner for damages sustained from their breach of contract. In many jurisdictions (I don't know about AZ specifically) you would also, even before going to court, be able to file a mechanic's or materialman's lien against the home for the amount owed.