Appellate Practice Attorney serving New York, NY
From what you've written (which is only one side of the story) it appears that the developer is breaching your contract. Assuming that you can't get them to comply, your options are to abandon the project and sue the developer for any damages you've suffered due to the breach of contract, to hire another develper to complete the scope of work and sue the first developer for anyting extra you had to pay over and above the contract price, or to pay the developer what they want and then sue to recover anything extra you paid once the job is done, claiming that the agreement to pay more is invalid because it was entered into under economic curess. This last option is probably the worst, since economic duress is very hard to establish.
Answered on Nov 15th, 2018 at 11:47 AM