If you have terminated the contract with the subcontractor, they are only due monies for work actually performed. Monies due over the term of the contract for work to be performed in the future is not likely to be due. However, this depends on the terms of the contract itself. If the breach of the contract caused damage to you, you may wish to consult an attorney regarding claims for damages that you may have against the subcontractor.